This paper has been prepared to explore the necessary planning to minimise delay factors on construction projects in
Kuwait during Covid-19. The data was obtained through face-to-face interviews. A case study was performed at West of Abdullah Al
Mubarak in Kuwait, identifying the major causes of delay on the project. The delay factors of the project were gathered from the
project manager and the study found the main delay factor was addressed and minimised by proper planning methods.